Shawnessy Station Buildings 1-3

Shawnessy Station Buildings 1-3
Schedule: Jul 2021 – Jun 2023
Prime Contractor: Trico Communities
Mechanical Contractor: MJS Mechanical
Engineer: Sunwise Engineering
Harvest Builders

Schedule: Dec 2020 – Feb 2021
Prime Contractor: Alston Properties
Mechanical Contractor: MJS Technical Services
Engineer: Smith + Anderson
Radiance Clinic

Schedule: January 2021 – March 2021
Prime Contractor: Owner
Mechanical Contractor: MJS Technical Services
Engineer: TMP Consulting Engineers
Courtyard 33 (CY33)

Schedule: Nov 2019 – Jun 2021
Prime Contractor: RNDSQR / Ledcor
Mechanical Contractor: MJS Mechanical
Engineer: TLJ Engineering Consulting Ltd
Kingsland Junction Buildings 1-3

Schedule: Apr 2019 – May 2021
Prime Contractor: Trico Communities
Mechanical Contractor: MJS Mechanical
Engineer: Sunwise Engineering
Kingsland Junction Buildings 4-5

Schedule: May 2020 – May 2022
Prime Contractor: Trico Communities
Mechanical Contractor: MJS Mechanical
Engineer: Sunwise Engineering
City of Calgary City Hall +15 Emergency Repairs

Schedule: March 2020 – April 2020
Prime Contractor: EllisDon
Mechanical Contractor: MJS Technical Services
Engineer: SNC Lavalin
Centennial Planetarium

Schedule: November 2017 – May 2019
Prime Contractor: EllisDon Construction Services Ltd.
Mechanical Contractor: MJS Mechanical
Engineer: Remedy Engineering
Legacy Village

Schedule: Oct 2018 – Sept 2019
Prime Contractor: Trico Developments
Mechanical Contractor: MJS Mechanical
Engineer: EMBE Consulting Engineers