MJS Mechanical Project Spotlight
CRA Call Centre Relocation
Schedule: Nov 2020 – April 2021
Prime Contractor: Chandos Construction
Mechanical Contractor: MJS Technical Services
Engineer: WSP
Project Description
Tenant fit out of 4 stories of an existing office tower at approximately 62,000 sq ft. The work was completed in an active building providing the typical challenges of noise and serviceability restrictions. MJS supplied and installed new plumbing fixtures for washrooms and kitchenettes on each floor, air conditioning for the data room, and local electric hot water tanks. The project required major ductwork relocation and new VAV boxes throughout the renovated space as well as perimeter radiation with zone control. The MJS team was able to collaborate with the GC to turn over a successful project.